Evolution Metals says missed payments left 36 tonnes of magnet metal at Korean ports
A four-tonne trial lot from Vietnam reached the factory. The supplier kept the shipping documents for three larger consignments invoiced at a combined $5.4 million.
Evolution Metals & Technologies said in its November 16 quarterly filing that 36 tonnes of neodymium-praseodymium metal had reached South Korean ports but remained in bonded storage. The U.S.-listed magnet maker attributed the delay to a shortage of working capital. It missed payments due on the shipments, and supplier Senri Trading retained the original bills of lading.
The metal came from SRE Vietnam under a May agreement that called for a four-tonne trial lot followed by monthly deliveries of 12 tonnes. Evolution prepaid the trial lot, which cleared Korean customs and reached its factory by September 30. The next three allotments arrived at port between September 11 and October 10. Evolution said it lacked title to those cargoes and was negotiating a payment and delivery schedule with Senri.
The distinction matters for Evolution’s expansion at Pohang. In a separate update on November 16, the company said the equipment for its new magnet lines had arrived and commissioning was underway. The equipment and the metal are separate deliveries. The quarterly filing gives no estimate of the delayed cargo’s effect on factory output.
What to watch
A payment agreement with Senri would address the immediate financing issue. Release of the shipping documents and delivery to the factory would establish when the 36 tonnes became available for production. The original schedule also called for another 48 tonnes through January 2027.